BrenX Ltd. (NASDAQ: BRNX) reported preliminary operating data from its flagship industrial project at Tempo Beverages in Israel showing that its 32 MWh bGen™ thermal energy storage system is supplying steam at a cost approximately 40% below a modeled heavy fuel oil steam baseline. The company estimates that if current performance is sustained, Tempo could save approximately $1.0 million annually, or about $15 million over 15 years, according to the release distributed via NEWMEDIAWIRE.
The preliminary results, reported on November 4, 2026, are based on five operating days from October 25 to 29, during which net energy cost savings for Tempo were about $18,200, or roughly $3,640 per operating day. The annual estimate assumes 280 operating days per year and is net of annual maintenance costs. These figures follow earlier production results showing the Tempo system reached approximately 85 tons of steam per operating day during commissioning, about 21% above the project's base case of approximately 70 tons.
The timing of the data is significant. In late October, the Dutch TTF benchmark for European natural gas rose above 100 euros per megawatt-hour, its highest level since 2022. For European manufacturers that burn gas to produce steam, those prices flow directly into operating costs. According to the International Energy Agency, Nearly 40% of fossil-fuel-based low- and medium-temperature industrial heat could be electrified cost-effectively, with thermal storage identified as an increasingly promising solution.
BrenX also developed a digital platform that gives Tempo live access to the system's steam output, electrical power, pressure and temperature, along with charging costs, energy savings and avoided carbon emissions. A built-in savings calculator lets users model results under different electricity tariffs. The company said that for a business introducing a new kind of industrial energy system, that transparency can help shorten the sales cycle.
Tempo is the first proof point in a broader strategy for BrenX, which rebranded from Brenmiller Energy in August and has expanded its focus to developing, owning, operating and optimizing energy assets. The company believes that demonstrating sustained customer savings could support broader adoption of its energy services model and the development of recurring revenue from industrial energy services. In Hungary, BrenX owns and is operating a 1.2 MWp solar facility in Kaposszekcső and has signed a definitive agreement to buy adjacent land for its planned first integrated energy resource center. In Israel, construction is underway on a 12 MWh bGen™ system at Wolfson Medical Center in Holon, designed to replace the hospital's fuel-oil boilers and expected to save approximately $1.5 million in annual energy costs.
The next milestone for investors is the completion of commissioning at Tempo and the start of commercial operations. After that, attention will turn to validating sustained operating performance and customer energy savings at Tempo, progress at Wolfson and new industrial customers in Europe. The preliminary results were originally published on Benzinga, and additional disclosures are available here. The original release can be viewed on www.newmediawire.com.