Phoenix Commercial Permit Timelines Often Exceed the Advertised 30 Days, Experts Warn

Business owners in Phoenix face longer-than-expected commercial building permit timelines due to overlooked administrative steps and municipal variations, which can delay project starts and increase costs.

Bay Area Metrowire Staff
••Real Estate
Phoenix Commercial Permit Timelines Often Exceed the Advertised 30 Days, Experts Warn

For business owners planning a tenant improvement in Phoenix, Arizona, the commonly cited 30-day commercial building permit timeline is a misleading benchmark, according to Mike Marden, a registered architect and licensed general contractor who founded WDS, a Phoenix-based integrated design-build firm. Marden notes that owners are typically surprised by the steps surrounding the city’s review rather than the review itself, and most of those steps never appear in a published timeline.

The 30-day figure is a reasonable starting point, but it rarely reflects the full duration from submission to approved permit. The Phoenix area has roughly 20 municipalities, each with its own review cycles. Some count calendar days, others business days, and some city offices are only open Monday through Thursday. A review listed as 27 business days at a city that does not work Fridays can stretch to five or six weeks on the calendar. Because of this variability, Marden’s team plans around the published worst case to protect both the firm and the client.

The bigger gap, according to Marden, is that a published review period usually covers only the technical review. Two other steps happen around it, and owners rarely hear about either. The first is preparing the submittal, which can take several days depending on the city’s online portal requirements—some want each discipline uploaded separately, others want individual sheets broken out, and some require the application to be completed in one sitting. The second is an administrative review, where city technicians check whether the submittal is complete. This check can take anywhere from three to 15 days and is generally not counted in the published review time. Only after it clears does the three- or five-week technical review begin.

Once plans are in the city’s hands, there is little an owner can do to speed up the review. Real time savings come earlier, during design, and depend largely on how quickly owners provide information and make decisions. Owners who follow the design team’s process and complete action items on time move into city review sooner.

Marden also points to a gap unrelated to the city: the time between getting plans approved and deciding who will build the project. Some owners rush to submit plans and then start looking for a general contractor during or after the review. If bids come back higher than expected, the owner may want to change the design, which extends the review and can even require the submittal to start over. Additionally, for a commercial project, the city will not release the permit until the owner names a licensed general contractor with a proper commercial license. An owner who hasn’t selected a contractor by then may go through a 30-day bid cycle while an approved permit sits waiting, and while lease or mortgage payments continue on a space that can’t be built out yet.

This is one reason Marden’s firm keeps design and construction on the same team, with plans prepared through WDS Architecture and costs reviewed as the design develops. When pricing is known along the way, owners are less likely to face a late redesign, and the permit can be released as soon as it is approved. WDS is an integrated design-build firm comprised of WDS Architecture PLLC and WDS Commercial LLC, subsidiaries of Marden Companies LLC.

For owners planning a buildout in the Phoenix area, Marden’s advice is to build these steps into the schedule from the start: plan for the published worst case, allow time for submittal prep and administrative review, and have a contractor in place before the permit is ready to be issued. Understanding these hidden steps can help business owners avoid costly delays and keep their projects on track.